Nebius’ $40B neocloud bet faces Microsoft-backed delay risks

On Thursday’s third-quarter earnings call, Nebius laid out $40 billion in planned 2027 capital spending, far above Wall Street’s expectations. The neocloud provider plans to fund the buildout with customer pre-payments and loans backed by customer contracts, effectively using future data center value to finance construction. CFO Maria Del Dado Alonso Sanchez named Microsoft and Meta as contracts that can be financed this way. Prepayments plus asset-backed financing of investment-grade contracts are expected to cover up to 85% of the $40-$45 billion 2027 capex spend, and Nebius ended Q3 with $7.4 billion in cash.

The plan depends on projects reaching capacity on schedule. CEO Arkady Volozh acknowledged the risk: “Building at this scale is hard, and delays are part of our industry right now. We are not immune.” That caution is pointed because Nebius‘s largest customer, Microsoft, is already tied to a delayed site. Microsoft is paying for AI compute capacity at a Vineland, New Jersey data center operated by third-party DataOne, in a contract worth up to $19.4 billion. Only just over half of that Microsoft capacity is now expected by the end of the year; the rest is planned for Q2 2027, after tranches originally meant for 2025 and 2026. Nebius attributes the delay to DataOne winding down temporary generation faster than expected as the site switches to Bloom Energy fuel cells.

DataOne‘s transition was not entirely voluntary. In August, Floodlight identified at least 45 natural gas generators running at the site without permits for gas generators. New Jersey regulators fined DataOne $1.1 million, finding the generators violated federal law. The facility also faces a noise-complaint lawsuit from nearby residents. Nebius‘s summary of the Microsoft contract says Microsoft can terminate affected service after a grace period if deadlines are missed and no alternative capacity is offered; the contract also includes financial penalties for late delivery. Nebius said Microsoft has been part of the planning process and has not publicly canceled, though it did not say whether Microsoft agreed to the new dates.

Microsoft‘s broader behavior suggests less patience. Bloomberg reported that Microsoft is tightening oversight on third-party projects run by Nebius, IREN, and Nscale, and debating whether to sign new agreements. Microsoft sent employees to the New Jersey site, and its own quarterly report said capex was lower than expected because of third-party delays. Bloomberg also reported that Microsoft will not use an option to more than double its Nscale agreement for a Texas data center and recently stopped being an anchor customer for Nscale’s planned Essex site after power delays.

Nebius argues the problems are concentrated in sites it does not control. Its own data centers are coming online on time or early, and those will supply most new capacity from 2027. CRO Marc Boroditsky said new deals signed in Q3 came with prepayments that more than cover the cost of capacity built behind them, and Nebius could tap prepayments for additional cash. Nebius forecast 2027 revenue of $12-$13 billion and expects pre-tax break-even by the fourth quarter. Q3 revenue was $981 million, up 571% year over year, though roughly a third came from a one-time payment tied to a new partnership model. Nebius cut its 2026 revenue forecast by $200 million to $3 billion, citing delays at third-party sites like New Jersey. Shares ended the day down 17%.